Building Project week 26 (completion 6 June)

The Kitchen and Servery layouts are now finalised, floor and wall finishes confirmed,and plasterings nearly finished. The new Narthex roof is being constructed and the new wall outside is nearly finished and will have railings added soon as well.The site meeting we had this week confirms that the buildersĀ are making really good headway and the planned handover after a clean and tidy up should be the week beginning 3 June. This week also Johnstone Paints (through Chris Green in our congregation) have very kindly donated all the paint we need (130 litres) – that’s a lot of cans to use and a lot of thanks to give. This was also the week when 2000 letters were put into envelopes and deliveries started to all the parish nearest to our Church